Satyaprakash Joshii wrote:and if he will be putting more user stories during the meeting itself , I will say ok if you want to add this buy the estimates are different.
Satyaprakash Joshii wrote: I will not worry and keeping doing work according to my estimates whether they are taken or not.
Useful advice but if senior developer is piled with work , then it will not work exactly at this.
[OCP 17 book] | [OCP 11 book] | [OCA 8 book] [OCP 8 book] [Practice tests book] [Blog] [JavaRanch FAQ] [How To Ask Questions] [Book Promos]
Other Certs: SCEA Part 1, Part 2 & 3, Core Spring 3, TOGAF part 1 and part 2
Saying that sort of thing would be a serious mistake. You should suck through your teeth like a builder and say, “Oooooooooooooooooh! There's a good three days' work there, Guv.” They will worry a lot less when it actually runs into the fourth day.Junilu Lacar wrote:. . . just because you said "I estimate that this will take me 2 days to finish," you MUST be done in two days. . . .
Junilu Lacar wrote:Estimates are not commitments either.
[OCP 17 book] | [OCP 11 book] | [OCA 8 book] [OCP 8 book] [Practice tests book] [Blog] [JavaRanch FAQ] [How To Ask Questions] [Book Promos]
Other Certs: SCEA Part 1, Part 2 & 3, Core Spring 3, TOGAF part 1 and part 2
Jeanne Boyarsky wrote:Early in my career, a manager told me that she needed a task done on Monday. I said it would be done on Wednesday. She kept repeating it needed to be done Monday. (I think this was a ploy to work the weekend.) I responded my saying it would be two days late. Guess when I delivered?
I know more now and can negotiate scope. But my approach at that time was at least entertaining!
Junilu Lacar wrote:The lack of transparency
[OCP 17 book] | [OCP 11 book] | [OCA 8 book] [OCP 8 book] [Practice tests book] [Blog] [JavaRanch FAQ] [How To Ask Questions] [Book Promos]
Other Certs: SCEA Part 1, Part 2 & 3, Core Spring 3, TOGAF part 1 and part 2
How many times do we have to go over this concept anyway? It seems we've tried to make this point numerous times in this thread but you keep coming back to using estimates as some kind measure of performance.
But my approach at that time was at least entertaining!
I wasn't willing to end the conversation making it sounding like I was promising to deliver on the date she "suggested."
[OCP 17 book] | [OCP 11 book] | [OCA 8 book] [OCP 8 book] [Practice tests book] [Blog] [JavaRanch FAQ] [How To Ask Questions] [Book Promos]
Other Certs: SCEA Part 1, Part 2 & 3, Core Spring 3, TOGAF part 1 and part 2
She kept repeating it needed to be done Monday.
I responded my saying it would be two days late.
I wasn't willing to end the conversation making it sounding like I was promising to deliver on the date she "suggested."
Satyaprakash Joshii wrote:What is a way of not ending such a conversation without "ok" if you are being told as you mentioned above and then you are told that again ?
[OCP 17 book] | [OCP 11 book] | [OCA 8 book] [OCP 8 book] [Practice tests book] [Blog] [JavaRanch FAQ] [How To Ask Questions] [Book Promos]
Other Certs: SCEA Part 1, Part 2 & 3, Core Spring 3, TOGAF part 1 and part 2
Satyaprakash Joshii wrote:My team , company can change in future but my technique is more important as it will be there with me irrespective of the company I work for. So , I will keep my technique correct in either case.
Campbell Ritchie wrote:You are going to end the conversations with, “All right, then, but it still won't work,” and start the next conversation with, “I told you so.”
That isn't good
Do we know whether it is only this particular team or department with that problem, or the whole company?Junilu Lacar wrote:. . . the manager and architect are of a fixed mindset . . .
This comes with the risk of you being labeled as argumentative. So you have to feel safe in your job to do this.
Do we know whether it is only this particular team or department with that problem, or the whole company?
Also, do the company worry when they find all their staff asking for references so they can apply elsewhere?
They have to change their mindset and meet you in "the middle". Only in that middle ground where the team can willingly and honestly agree to the work they will own can there be any hope of bringing back rationality, transparency, honesty, and integrity into the situation.
[OCP 17 book] | [OCP 11 book] | [OCA 8 book] [OCP 8 book] [Practice tests book] [Blog] [JavaRanch FAQ] [How To Ask Questions] [Book Promos]
Other Certs: SCEA Part 1, Part 2 & 3, Core Spring 3, TOGAF part 1 and part 2
So there I was, trapped in the jungle. And at the last minute, I was saved by this tiny ad:
The Low Tech Laboratory Movie Kickstarter is LIVE NOW!
https://www.kickstarter.com/projects/paulwheaton/low-tech
|